| Action Date | Action Description |
|---|---|
| Jan 24, 2019 | Assent Application Received |
| Jan 24, 2019 | Administrative Review for Completeness |
| Jan 30, 2019 | Team Review for Completeness |
| Jan 30, 2019 | Deficient Application - Owner Notification Sent |
| Feb 06, 2019 | Deficiency Response Received |
| Feb 13, 2019 | Team Review for Completeness |
| Feb 13, 2019 | Application Accepted |
| Mar 04, 2019 | HPHC Historical Preservation No Effect |
| Mar 04, 2019 | HPHC Review Pending |
| Mar 18, 2019 | Plans Received |
| Mar 19, 2019 | Biologist Report |
| Mar 21, 2019 | Typist for Processing |
| Mar 21, 2019 | Executive Sign Off |
| Mar 21, 2019 | Sent to Photo Copy |
| Mar 21, 2019 | Permit Approved |
| Apr 02, 2019 | Land Evidence Date |