| Action Date | Action Description |
|---|---|
| Mar 02, 2021 | Assent Application Received |
| Mar 08, 2021 | Administrative Review for Completeness |
| Mar 11, 2021 | Aquaculture Administrative Review |
| Mar 11, 2021 | Application Accepted |
| Mar 15, 2021 | Project Manager |
| Mar 15, 2021 | 30 day Public Notice Issued |
| Apr 15, 2021 | Public Notice End Date |
| Aug 30, 2022 | Additional Information Received |
| Sep 12, 2022 | Aquaculture Report |
| Sep 14, 2022 | Additional Information Received |
| Sep 14, 2022 | Executive Sign Off |
| Sep 14, 2022 | Permit Approved |
| Sep 14, 2022 | Permit Mailed |
| Dec 05, 2022 | Aquaculture Lease Received |
| Feb 21, 2023 | Aquaculture Lease Payment |
| Feb 21, 2023 | Aquaculture Yearly Questionnaire |
| Jan 04, 2024 | Aquaculture Lease Payment |
| Jan 17, 2024 | Aquaculture Yearly Questionnaire |
| Jan 17, 2024 | Aquaculture Bond Received |
| Jan 02, 2025 | Aquaculture Yearly Questionnaire |
| Jan 02, 2025 | Aquaculture Lease Payment |