| Action Date | Action Description |
|---|---|
| Mar 30, 2021 | Preliminary Determination Request (Coastal) |
| Mar 31, 2021 | Administrative Review for Completeness |
| Apr 05, 2021 | Bio Team Review for Completeness |
| May 06, 2021 | Assent Application Received |
| May 06, 2021 | Administrative Review for Completeness |
| May 25, 2021 | Application Accepted |
| May 27, 2021 | Project Manager |
| Jun 10, 2021 | HPHC Review Pending |
| Jun 10, 2021 | HPHC Historical Preservation No Effect |
| Aug 03, 2021 | Stipulation Package from Biologist |
| Aug 03, 2021 | Biologist Report |
| Aug 06, 2021 | Typist for Processing |
| Aug 06, 2021 | Executive Sign Off |
| Aug 06, 2021 | Sent to Photo Copy |
| Aug 06, 2021 | Permit Approved |
| Aug 10, 2021 | Permit Mailed |
| Jan 18, 2022 | Land Evidence Date |