| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Sep 15, 2021 | Assent Application Received |
| Sep 20, 2021 | Administrative Review for Completeness |
| Nov 04, 2021 | Bio Team Review for Completeness |
| Nov 04, 2021 | Application Accepted |
| Nov 05, 2021 | Project Manager |
| Nov 05, 2021 | Category A* (Docks) |
| Nov 17, 2021 | HPHC Review Pending |
| Nov 17, 2021 | HPHC Historical Preservation No Effect |
| Dec 03, 2021 | US Army Corps of Engineers Approval Received |
| Dec 06, 2021 | 30 day Public Notice Issued |
| Jan 06, 2022 | Public Notice End Date |
| Mar 03, 2022 | Additional Information Received |
| Apr 04, 2022 | Engineering Report |
| Apr 04, 2022 | Mail Agenda Notice |
| Apr 06, 2022 | Supervisor Biologist SignOff |
| Apr 06, 2022 | Supervisor Engineer SignOff |
| Apr 07, 2022 | Executive Signoff of Staff Reports |
| Apr 12, 2022 | Council Approval Granted |
| Apr 12, 2022 | Semi-Monthly Meeting Date Scheduled |
| Nov 02, 2022 | Stipulation Package by Engineer |
| Nov 09, 2022 | Legal Response/Decision |
| Nov 09, 2022 | 30 Day Appeal Notification to Owner |
| Jan 17, 2023 | Permit Approved |
| Jan 19, 2023 | Permit Mailed |
| Oct 20, 2023 | Land Evidence Date |