| Action Date | Action Description |
|---|---|
| Sep 22, 2022 | Assent Application Received |
| Oct 24, 2022 | Administrative Review for Completeness |
| Oct 24, 2022 | Deficient Application - Owner Notification Sent |
| Nov 04, 2022 | Deficiency Response Received |
| Nov 18, 2022 | Bio Team Review for Completeness |
| Nov 21, 2022 | Deficient Application - Owner Notification Sent |
| Jul 05, 2023 | Phone Call |
| Jul 05, 2023 | Correspondence Mailed/Faxed/E-mailed |
| Oct 18, 2023 | Deficiency Response Received |
| Oct 18, 2023 | Bio Team Review for Completeness |
| Oct 18, 2023 | Application Accepted |
| Oct 18, 2023 | Project Manager |
| Oct 18, 2023 | HPHC Historical Preservation No Effect |
| Nov 09, 2023 | Correspondence Mailed/Faxed/E-mailed |
| Dec 20, 2023 | Additional Information Requested from Applicant |
| Feb 02, 2024 | Note to File |
| Mar 07, 2024 | Biologist Report |
| Mar 08, 2024 | Typist for Processing |
| Mar 08, 2024 | Executive Sign Off |
| Mar 08, 2024 | Sent to Photo Copy |
| Mar 08, 2024 | Permit Approved |
| Mar 12, 2024 | Permit Mailed |
| Apr 08, 2024 | Land Evidence Date |