| Action Date | Action Description |
|---|---|
| Dec 20, 2022 | Maintenance Certification Request |
| Dec 21, 2022 | Administrative Review for Completeness |
| Dec 27, 2022 | Eng Team Review for Completeness |
| Dec 27, 2022 | Deficient Application - Owner Notification Sent |
| Jan 03, 2023 | Deficient Application Picked Up |
| Feb 16, 2023 | Deficiency Response Received |
| Feb 27, 2023 | Eng Team Review for Completeness |
| Feb 27, 2023 | Application Accepted |
| Feb 27, 2023 | Project Manager |
| Mar 07, 2023 | Engineering Report |
| Mar 15, 2023 | HPHC Historical Preservation No Effect |
| Mar 27, 2023 | Typist for Processing |
| Mar 27, 2023 | Executive Sign Off |
| Mar 27, 2023 | Sent to Photo Copy |
| Mar 27, 2023 | Permit Approved |
| Mar 30, 2023 | Permit Mailed |
| Oct 04, 2023 | Land Evidence Date |