| Action Date | Action Description |
|---|---|
| Jan 15, 2013 | Assent Application Received |
| Jan 15, 2013 | Administrative Review for Completeness |
| Jan 16, 2013 | Team Review for Completeness |
| Jan 16, 2013 | Deficiency - Phone Call to Applicant/Owner |
| Jan 17, 2013 | Deficient Application Picked Up |
| Mar 11, 2013 | Deficiency Response Received |
| Mar 12, 2013 | Team Review for Completeness |
| Mar 18, 2013 | Team Review for Completeness |
| Mar 18, 2013 | Deficient Application - Owner Notification Sent |
| Apr 09, 2013 | Deficient Application Picked Up |
| Apr 19, 2013 | Deficiency Response Received |
| Apr 24, 2013 | Team Review for Completeness |
| Apr 26, 2013 | Additional Information Received |
| Apr 26, 2013 | Application Accepted |
| May 06, 2013 | HPHC Historical Preservation No Effect |
| May 10, 2013 | 30 day Public Notice Issued |
| Jun 10, 2013 | Public Notice End Date |
| Jun 20, 2013 | Category A* (Docks) |
| Jun 20, 2013 | Typist for Processing |
| Jun 20, 2013 | Biologist Report |
| Jun 20, 2013 | Permit Approved |
| Jun 25, 2013 | Executive Sign Off |
| Jun 25, 2013 | Sent to Photo Copy |
| Jun 25, 2013 | US Army Corps of Engineers Approval Received |
| Aug 01, 2013 | Land Evidence Date |