| Action Date | Action Description |
|---|---|
| Nov 22, 2013 | Assent Application Received |
| Nov 25, 2013 | Administrative Review for Completeness |
| Dec 16, 2013 | Correspondence Received |
| Jan 22, 2014 | Additional Information Received |
| Jan 22, 2014 | Application Accepted |
| Jan 22, 2014 | Team Review for Completeness |
| Feb 04, 2014 | 30 day Public Notice Issued |
| Feb 20, 2014 | HPHC Historical Preservation No Effect |
| Mar 04, 2014 | Public Notice End Date |
| Mar 11, 2014 | Engineering Report |
| Mar 14, 2014 | Typist for Processing |
| Mar 14, 2014 | Permit Approved |
| Mar 18, 2014 | Executive Sign Off |
| Mar 18, 2014 | Sent to Photo Copy |
| Apr 03, 2014 | Land Evidence Date |
| Apr 09, 2014 | Additional Information Received |