| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Nov 18, 2020 | Assent Application Received |
| Nov 20, 2020 | Administrative Review for Completeness |
| Nov 25, 2020 | Category A* (Docks) |
| Dec 01, 2020 | Bio Team Review for Completeness |
| Dec 02, 2020 | Application Accepted |
| Dec 02, 2020 | Project Manager |
| Dec 02, 2020 | Category A* (Docks) |
| Dec 02, 2020 | 30 day Public Notice Issued |
| Dec 23, 2020 | HPHC Review Pending |
| Dec 23, 2020 | HPHC Historical Preservation No Effect |
| Jan 02, 2021 | Public Notice End Date |
| Jan 21, 2021 | Plans Received |
| Jan 29, 2021 | Biologist Report |
| Feb 01, 2021 | Mail Agenda Notice |
| Feb 04, 2021 | Supervisor Biologist SignOff |
| Feb 04, 2021 | Supervisor Engineer SignOff |
| Feb 04, 2021 | Executive Signoff of Staff Reports |
| Feb 09, 2021 | Semi-Monthly Meeting Date Scheduled |
| Feb 10, 2021 | Typist for Processing |
| Feb 10, 2021 | Executive Sign Off |
| Feb 10, 2021 | Sent to Photo Copy |
| Feb 10, 2021 | Permit Approved |
| Feb 19, 2021 | Land Evidence Date |