| Action Date | Action Description |
|---|---|
| Dec 12, 2008 | Assent Application Received |
| Dec 15, 2008 | Administrative Review for Completeness |
| Dec 29, 2008 | Team Review for Completeness |
| Dec 29, 2008 | Application Accepted |
| Dec 29, 2008 | Category A* (Docks) |
| Jan 05, 2009 | 30 day Public Notice Issued |
| Jan 27, 2009 | Plans Received |
| Feb 04, 2009 | Public Notice End Date |
| Feb 12, 2009 | HPHC Historical Preservation No Effect |
| Feb 20, 2009 | Dock Meeting -- Approval |
| Feb 23, 2009 | US Army Corp of Engineers Permit Date |
| Feb 25, 2009 | US Army Corps of Engineers Approval Received |
| Mar 02, 2009 | Biologist Report |
| Mar 02, 2009 | Engineering Report |
| Mar 03, 2009 | Typist for Processing |
| Mar 03, 2009 | Executive Sign Off |
| Mar 03, 2009 | Sent to Photo Copy |
| Mar 03, 2009 | Permit Approved |
| Mar 13, 2009 | Land Evidence Date |
| May 18, 2009 | Commencement of Work Notice received |
| Feb 22, 2012 | Modification Request |
| Feb 23, 2012 | Administrative Review for Completeness |
| Feb 27, 2012 | Team Review for Completeness |
| Feb 27, 2012 | Team Review for Completeness |
| Mar 09, 2012 | HPHC Historical Preservation No Effect |
| Mar 19, 2012 | 30 day Public Notice Issued |
| Apr 19, 2012 | Public Notice End Date |
| Jun 07, 2012 | Plans Received |
| Jun 08, 2012 | Biologist Report |
| Jun 08, 2012 | Engineering Report |
| Jun 11, 2012 | Typist for Processing |
| Jun 11, 2012 | Executive Sign Off |
| Jun 11, 2012 | Sent to Photo Copy |
| Jun 11, 2012 | Modification Approved |
| Jun 27, 2013 | Duplicate Original Assent requested/mailed |
| Jul 11, 2013 | Land Evidence Date |