| Action Date | Action Description |
|---|---|
| Jan 25, 2010 | Assent Application Received |
| Jan 25, 2010 | Administrative Review for Completeness |
| Jan 26, 2010 | Team Review for Completeness |
| Jan 26, 2010 | Application Accepted |
| Feb 12, 2010 | HPHC Historical Preservation No Effect |
| Mar 03, 2010 | 30 day Public Notice Issued |
| Apr 03, 2010 | Public Notice End Date |
| Apr 05, 2010 | Dock Meeting -- Approval |
| Apr 05, 2010 | Category B assigned |
| Nov 24, 2010 | Plans Received |
| Apr 08, 2011 | Biologist Report |
| Apr 11, 2011 | Typist for Processing |
| Apr 11, 2011 | Executive Sign Off |
| Apr 11, 2011 | Sent to Photo Copy |
| Apr 11, 2011 | Permit Approved |
| Jun 16, 2011 | US Army Corps of Engineers Approval Received |
| Jul 27, 2011 | Land Evidence Date |
| May 02, 2019 | Extension of Permit Request |
| May 17, 2019 | Enforcement Compliance Inspection Required |
| May 17, 2019 | Process Extension |
| May 17, 2019 | Extension Approved |