| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jun 13, 2017 | Assent Application Received |
| Jun 13, 2017 | Administrative Review for Completeness |
| Jun 14, 2017 | Additional Information Requested from Applicant |
| Jul 17, 2017 | Additional Information Received |
| Jul 18, 2017 | Team Review for Completeness |
| Jul 18, 2017 | Application Accepted |
| Jul 28, 2017 | HPHC Historical Preservation No Effect |
| Aug 01, 2017 | Additional Information Received |
| Aug 02, 2017 | 30 day Public Notice Issued |
| Aug 11, 2017 | Site Inspection |
| Aug 28, 2017 | Objections/Comments Received |
| Sep 03, 2017 | Public Notice End Date |
| Sep 08, 2017 | Objections/Comments Received |
| Sep 15, 2017 | Meeting Held |
| Oct 26, 2017 | Additional Information Requested from Applicant |
| Dec 06, 2017 | US Army Corps of Engineers Approval Received |
| Feb 08, 2018 | Additional Information Requested from Applicant |
| Jul 27, 2018 | Additional Information Requested from Applicant |
| Jul 30, 2018 | Additional Information Received |
| Aug 06, 2018 | Additional Information Requested from Applicant |
| Aug 16, 2018 | Additional Information Received |
| Aug 24, 2018 | 30 day Public Notice Issued |
| Sep 14, 2018 | Objections/Comments Received |
| Sep 24, 2018 | Public Notice End Date |
| Nov 08, 2018 | Comments Received |
| Jan 22, 2019 | Additional Information Received |
| Jan 29, 2019 | Dock Meeting -- Approval |
| Jan 31, 2019 | Plans Received |
| Feb 04, 2019 | Biologist Report |
| Feb 06, 2019 | Typist for Processing |
| Feb 06, 2019 | Executive Sign Off |
| Feb 06, 2019 | Sent to Photo Copy |
| Feb 06, 2019 | Permit Approved |
| Feb 19, 2019 | Land Evidence Date |