| Action Date | Action Description |
|---|---|
| Jun 09, 2020 | Assent Application Received |
| Jun 09, 2020 | Administrative Review for Completeness |
| Jun 17, 2020 | Bio Team Review for Completeness |
| Jun 17, 2020 | Deficient Application - Owner Notification Sent |
| Jun 24, 2020 | Additional Information Received |
| Jul 01, 2020 | Deficiency Response Received |
| Jul 13, 2020 | Bio Team Review for Completeness |
| Jul 13, 2020 | Application Accepted |
| Jul 24, 2020 | HPHC Review Pending |
| Jul 24, 2020 | HPHC Historical Preservation No Effect |
| Jul 28, 2020 | Project Manager |
| Aug 11, 2020 | Additional Information Requested from Applicant |
| Aug 17, 2020 | Phone Call |
| Aug 18, 2020 | Additional Information Requested from Applicant |
| Aug 18, 2020 | Plans Received |
| Aug 20, 2020 | Plans Received |
| Sep 03, 2020 | Additional Information Received |
| Sep 09, 2020 | Additional Information Received |
| Sep 11, 2020 | Plans Received |
| Sep 21, 2020 | Typist for Processing |
| Sep 21, 2020 | Executive Sign Off |
| Sep 21, 2020 | Sent to Photo Copy |
| Sep 21, 2020 | Permit Approved |
| Sep 21, 2020 | Biologist Report |
| Nov 16, 2020 | Land Evidence Date |