| Action Date | Action Description |
|---|---|
| Legal Response/Decision | |
| Land Evidence Date | |
| Dock Post-Construction Certification by Engineer Required. | |
| Jun 16, 2025 | Assent Application Received |
| Jun 18, 2025 | Administrative Review for Completeness |
| Jul 01, 2025 | Bio Team Review for Completeness |
| Jul 01, 2025 | Application Accepted |
| Jul 01, 2025 | Project Manager |
| Jul 15, 2025 | HPHC Historical Preservation No Effect |
| Aug 19, 2025 | Additional Information Received |
| Sep 09, 2025 | 30 day Public Notice Issued |
| Oct 08, 2025 | Mail Agenda Notice |
| Oct 08, 2025 | Additional Information Received |
| Oct 08, 2025 | Comments Received |
| Oct 09, 2025 | Public Notice End Date |
| Oct 09, 2025 | Biologist Report |
| Oct 28, 2025 | Semi-Monthly Meeting Date Scheduled |
| Oct 28, 2025 | Council Approval Granted |
| Nov 03, 2025 | Stipulation Package from Biologist |
| Nov 06, 2025 | Typist for Processing |
| Nov 06, 2025 | Executive Sign Off |
| Nov 06, 2025 | Sent to Photo Copy |
| Nov 06, 2025 | Permit Approved |
| Nov 07, 2025 | Permit Mailed |