| Action Date | Action Description |
|---|---|
| Jul 11, 2005 | Assent Application Received |
| Jul 12, 2005 | Administrative Review for Completeness |
| Jul 19, 2005 | Team Review for Completeness |
| Jul 19, 2005 | Application Accepted |
| Jul 19, 2005 | Category B assigned |
| Aug 12, 2005 | Historical Preservation Approval Granted |
| Nov 07, 2005 | Additional Information Received |
| Jan 11, 2006 | 30-Day Notification of Cancellation letter |
| Jan 25, 2006 | Certified Receipt Received |
| Jan 30, 2006 | Correspondence Received |
| Feb 10, 2006 | Plans Received |
| Feb 16, 2006 | 30 day Public Notice Issued |
| Mar 13, 2006 | Correspondence Received |
| Mar 14, 2006 | US Army Corp of Engineers Permit Date |
| Mar 15, 2006 | US Army Corps of Engineers Approval Received |
| Mar 15, 2006 | Public Notice End Date |
| Apr 14, 2006 | Biologist Report |
| Apr 14, 2006 | Engineering Report |
| May 08, 2006 | Supervisor Biologist SignOff |
| May 08, 2006 | Supervisor Engineer SignOff |
| May 09, 2006 | Executive Sign Off |
| May 11, 2006 | Ready to Schedule Semi-Monthly Meeting |
| May 11, 2006 | Mail Agenda Notice |
| May 23, 2006 | Semi-Monthly Meeting Held |
| May 23, 2006 | Council Approval Granted |
| May 23, 2006 | Stipulation Package from Biologist |
| May 23, 2006 | Stipulation Package by Engineer |
| May 23, 2006 | Semi-Monthly Meeting Date Scheduled |
| Jun 01, 2006 | Typist for Processing |
| Jun 01, 2006 | Executive Sign Off |
| Jun 01, 2006 | Sent to Photo Copy |
| Jun 01, 2006 | Permit Approved |
| Jun 12, 2006 | Legal Response/Decision |
| Aug 25, 2006 | Land Evidence Date |
| Sep 01, 2006 | Modification Request |
| Sep 01, 2006 | Administrative Review for Completeness |
| Sep 08, 2006 | Team Review for Completeness |
| Sep 08, 2006 | Engineering Report |
| Sep 08, 2006 | Modification Approved |
| Sep 11, 2006 | Typist for Processing |
| Sep 11, 2006 | Executive Sign Off |
| Sep 11, 2006 | Sent to Photo Copy |
| Sep 18, 2006 | Land Evidence Date |