| Action Date | Action Description |
|---|---|
| Jul 22, 2005 | Assent Application Received |
| Jul 27, 2005 | Administrative Review for Completeness |
| Jul 27, 2005 | Team Review for Completeness |
| Jul 27, 2005 | Application Accepted |
| Jul 27, 2005 | Category A* (Docks) |
| Aug 12, 2005 | HPHC Review Pending |
| Aug 12, 2005 | Historical Preservation Approval Granted |
| Sep 16, 2005 | 30 day Public Notice Issued |
| Sep 16, 2005 | Plans Received |
| Oct 12, 2005 | Objections/Comments Received |
| Oct 14, 2005 | Public Notice End Date |
| Nov 07, 2005 | Additional Information Requested from Applicant |
| Nov 14, 2005 | Entry of Appearance Received |
| Dec 09, 2005 | Biologist Report |
| Dec 09, 2005 | Engineering Report |
| Dec 12, 2005 | Executive Sign Off |
| Jan 11, 2006 | US Army Corp of Engineers Permit Date |
| Jan 12, 2006 | US Army Corps of Engineers Approval Received |
| Jan 12, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Jan 12, 2006 | Mail Agenda Notice |
| Jan 24, 2006 | Semi-Monthly Meeting Held |
| Jan 24, 2006 | Council Approval Granted |
| Jan 24, 2006 | Semi-Monthly Meeting Date Scheduled |
| Jan 31, 2006 | Legal Response/Decision |
| May 16, 2006 | Stipulation Package from Biologist |
| May 16, 2006 | Stipulation Package by Engineer |
| May 17, 2006 | Typist for Processing |
| May 17, 2006 | Executive Sign Off |
| May 17, 2006 | Sent to Photo Copy |
| May 17, 2006 | Permit Approved |
| Jun 08, 2006 | Land Evidence Date |
| Feb 11, 2009 | Extension of Permit Request |
| May 12, 2009 | Enforcement Compliance Inspection Required |
| May 12, 2009 | Extension Approved |
| Mar 01, 2010 | Extension of Permit Request |
| Mar 18, 2010 | Enforcement Compliance Inspection Required |
| Mar 18, 2010 | Extension Toll letter mailed |