| Action Date | Action Description |
|---|---|
| Jul 21, 2021 | Assent Application Received |
| Sep 24, 2021 | Administrative Review for Completeness |
| Sep 24, 2021 | Additional Information Received |
| Sep 28, 2021 | Bio Team Review for Completeness |
| Sep 28, 2021 | Application Accepted |
| Sep 28, 2021 | Project Manager |
| Sep 29, 2021 | Biologist Report |
| Oct 01, 2021 | Engineering Report |
| Oct 01, 2021 | Stipulation Package by Engineer |
| Oct 04, 2021 | CHA -- application modified due to CHA info |
| Oct 04, 2021 | Finding Of No Significant Impact (FONSI) |
| Oct 06, 2021 | Permit Mailed |
| Jan 25, 2022 | HPHC Review Pending |
| Jan 25, 2022 | HPHC Historical Preservation No Effect |