| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Oct 19, 2023 | Assent Application Received |
| Oct 24, 2023 | Administrative Review for Completeness |
| Oct 31, 2023 | Eng Team Review for Completeness |
| Oct 31, 2023 | Project Manager |
| Oct 31, 2023 | Application Accepted |
| Nov 07, 2023 | HPHC Historical Preservation No Effect |
| Dec 06, 2023 | 30 day Public Notice Issued |
| Jan 01, 2024 | Public Notice End Date |
| Feb 09, 2024 | Scheduled for Section 110 Review meeting |
| Mar 25, 2024 | Additional Information Received |
| Apr 15, 2024 | 30 day Public Notice Issued |
| May 10, 2024 | Dock/1.1.6 Review approval |
| May 15, 2024 | Public Notice End Date |
| Jun 11, 2024 | Engineering Report |
| Jun 21, 2024 | Typist for Processing |
| Jun 21, 2024 | Executive Sign Off |
| Jun 21, 2024 | Sent to Photo Copy |
| Jun 21, 2024 | Permit Approved |
| Jun 25, 2024 | Permit Mailed |
| Oct 08, 2024 | Land Evidence Date |