| Action Date | Action Description |
|---|---|
| May 10, 2019 | Assent Application Received |
| May 13, 2019 | Administrative Review for Completeness |
| May 17, 2019 | Team Review for Completeness |
| May 17, 2019 | Deficient Application - Owner Notification Sent |
| Aug 13, 2019 | Deficiency Response Received |
| Aug 16, 2019 | Team Review for Completeness |
| Aug 16, 2019 | Application Accepted |
| Aug 19, 2019 | Category B assigned |
| Aug 26, 2019 | 30 day Public Notice Issued |
| Sep 06, 2019 | HPHC Review Pending |
| Sep 06, 2019 | HPHC Historical Preservation No Effect |
| Sep 26, 2019 | Public Notice End Date |
| Jan 03, 2020 | Note to File |
| Jan 24, 2020 | Correspondence Mailed/Faxed/E-mailed |
| Feb 14, 2020 | Correspondence Mailed/Faxed/E-mailed |
| Feb 17, 2020 | Correspondence Received |
| Mar 11, 2020 | Additional Information Requested from Applicant |
| Mar 16, 2020 | Additional Information Requested from Applicant |
| Mar 31, 2020 | Application Cancelled |
| Mar 31, 2020 | Biologist Report |
| Mar 31, 2020 | Engineering Report |