| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Jul 17, 2025 | Assent Application Received |
| Jul 17, 2025 | CHA Worksheet received |
| Jul 22, 2025 | Administrative Review for Completeness |
| Aug 21, 2025 | Eng Team Review for Completeness |
| Aug 21, 2025 | Project Manager |
| Aug 21, 2025 | Application Accepted |
| Sep 05, 2025 | HPHC Historical Preservation No Effect |
| Oct 09, 2025 | 30 day Public Notice Issued |
| Nov 09, 2025 | Public Notice End Date |
| Nov 18, 2025 | Comments Received |
| Nov 21, 2025 | Public Notice End Date Extension Granted |
| Nov 28, 2025 | Engineering Report |
| Mar 30, 2026 | Typist for Processing |
| Mar 30, 2026 | Executive Sign Off |
| Mar 30, 2026 | Sent to Photo Copy |
| Mar 30, 2026 | Permit Approved |
| Apr 01, 2026 | Permit Mailed |