| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Nov 17, 2025 | Assent Application Received |
| Nov 18, 2025 | Administrative Review for Completeness |
| Dec 12, 2025 | Bio Team Review for Completeness |
| Dec 15, 2025 | Deficient Application - Owner Notification Sent |
| Dec 22, 2025 | Correspondence Received |
| Mar 27, 2026 | Deficiency Response Received |
| Apr 10, 2026 | Bio Team Review for Completeness |
| Apr 10, 2026 | Application Accepted |
| May 08, 2026 | Biologist Report |
| May 20, 2026 | HPHC Historical Preservation No Effect |
| May 22, 2026 | Executive Sign Off |
| May 22, 2026 | Sent to Photo Copy |
| May 22, 2026 | Permit Approved |
| May 22, 2026 | Typist for Processing |
| May 26, 2026 | Permit Mailed |