| Action Date | Action Description |
|---|---|
| Executive Sign Off | |
| Sent to Photo Copy | |
| Jun 12, 2026 | Maintenance Certification Request |
| Jun 15, 2026 | Administrative Review for Completeness |
| Jun 16, 2026 | Eng Team Review for Completeness |
| Jun 16, 2026 | Bio Team Review for Completeness |
| Jun 16, 2026 | Project Manager |
| Jun 16, 2026 | HPHC Historical Preservation No Effect |
| Jun 18, 2026 | Additional Information Received |
| Jun 23, 2026 | Additional Information Received |
| Jun 25, 2026 | Application Accepted |
| Jun 29, 2026 | Typist for Processing |