| Action Date | Action Description |
|---|---|
| Executive Sign Off | |
| Sent to Photo Copy | |
| Aug 12, 2026 | Assent Application Received |
| Aug 18, 2026 | Administrative Review for Completeness |
| Aug 21, 2026 | Additional Information Requested from Applicant |
| Sep 01, 2026 | Additional Information Received |
| Sep 01, 2026 | Additional Information Requested from Applicant |
| Sep 02, 2026 | Plans Received |
| Sep 02, 2026 | Bio Team Review for Completeness |
| Sep 02, 2026 | Application Accepted |
| Sep 02, 2026 | Project Manager |
| Sep 30, 2026 | HPHC Historical Preservation No Effect |
| Oct 28, 2026 | Additional Information Received |
| Nov 05, 2026 | Biologist Report |
| Nov 06, 2026 | Typist for Processing |